Answers to August 11th “Just for Fun” quiz:
a) 38 units will be put together to create the temporary K-4 school. 4 to 6 units will arrive at a time throughout the month of September. Consigli is working with MassDOT (Department of Transportation) and the Lincoln Police Department to create a transport and traffic plan.
b) 204 footings are being poured to support the temporary structure. They are being poured at a rate of 20 – 25/day. At the end of the project (in 3 years) they will all be removed and the field restored.
c) This is not a sign for lost Lincoln Minutemen! It is the meeting place for the construction team. Later in the project there will be a construction trailer.