Not Our First Rodeo…

Interior DesignAt the January 23rd SBC meeting, the SBC got a look at design concepts for the the interior of the school.  SMMA talked about choosing interior finishes that 1) create a calmer visual environment; 2) are durable; and 3) stay within our budget. This is made a bit more challenging by the fact that this is a renovation project, and that a number of colorful items will remain in place (i.e. teal countertops and cabinets in some rooms). As the interior is planned, it is important to think about future repairs and replacement when choosing the finishes, and later, the furniture. For example, we don’t want to specify 400 kiwi green chairs only to discover that a) the color will soon be discontinued, or b) that in a few years the “kiwi” of 2019 reminds us too much of the “avocado” of 1979. Fortunately, our administrative team has spent the last several years making these kinds of decisions for the Hanscom Primary and Middle Schools. We are able to draw on this depth of experience and the lessons learned.

Project ScheduleOur Construction Manager, Consigli, presented two important pieces of information at the meeting:

  1. Their cost estimate for the project (based on the Schematic Design phase) came in at essentially the same cost as the prior two estimates by SMMA and Daedalus. There will be another round of cost estimates in late March at the end of the Design Development phase.
  2. Consigli believes that the project can be completed by the start of the 2022/23 school year.  This is about six months earlier than previously planned (the image above shows a comparison of the old and new project schedules). This is one advantage of using a construction manager versus the “design, bid, build” construction method. Consigli is on board now, is part of the detailed investigation of existing conditions, and can help solve problems before difficult (or costly) issues arise.

Site Work: A Site Plan working group was brought together to think through refinements to the site plan. The initial meeting included representation from SMMA, Daedalus, the administrative team, the Conservation Commission, Parks & Recreation, the Roadway & Traffic Committee, the Cycling Safety Committee, and the SBC. The group will examine site related issues and bring ideas and recommendations to the SBC for its consideration.

0 Comments

There are no comments yet

Thoughts? Comments? Questions?

Discover more from Lincoln School Building Project

Subscribe now to keep reading and get access to the full archive.

Continue reading