Project Milestones

Inside the Learning Commons

Although all preK-8 students will be in the renovated school this fall, the School Building Committee anticipates that big work (installation of PV panels and connectivity) and small (punch list items) will continue on the Lincoln School campus for about another year. Here are some major milestones to watch for:

  • Furniture and equipment for grades K – 4 will move out of the modular school between June 22 and July 3.
  • The modular units will be removed from campus between July 25 and August 12.
  • About 25% of the photovoltaic (PV) panels are expected to arrive soon. Supply chain issues have slowed down delivery. Installation will begin on the Middle School gym.
  • All the PV panels should be installed and on line by next spring/summer.

The project team and SBC continue to closely monitor supply chain issues, schedule, and budget.

Click here for the slide deck from this past week’s meeting, and here for the June photo gallery.