Skip to content Skip to left sidebar Skip to footer

Tag: Site Plan

Something’s Happening Here…

Last week, Consigli began site preparations for the “Enabling Phase” of the school project: The northern portion of the center field (future location of the temporary classrooms) was fenced off; screens were installed in the drainage grates to filter out construction debris, and; protective materials were placed around wetlands areas. Stay tuned!

Reminder: Next SBC meeting is on August 14th.

See the Latest Design Updates!

At last Wednesday’s meeting, EwingCole and SMMA shared the latest updates to both interior and exterior designs for the center part of the school. The presentation (which can be seen in its entirety here) included:

  • Light studies of the Learning Commons: The Learning Commons have an east to west orientation, and light control is important in the early morning and late afternoon. The SBC reviewed two options for exterior shading, and chose the horizontal fin screen pictured in the images. There will also be internal shades to allow light to be blocked out for presentations.
  • Exterior studies of building materials.
  • Interior studies of the new Media Center and the corridor that will connect the Learning Commons to the Smith end of the building (the “K – 4 Gallery”).

Upcoming Meetings:

  • May 28th: Planning Board, 7pm, Town Offices. This is the initial review of the plan for the modulars. The Conservation Committee approved the plans on May 22nd.
  • June 5th: School Building Committee, 7pm, Hartwell.
  • June 11th: Planning Board, 7pm, Town Offices. Final hearing and vote to approve the plan for the modulars.

 

Design Updates…

The design team is continuing to work through a myriad of site plan, systems, and design details. Following are some updated images that were shown at Wednesday’s meeting.  To see the entire slide deck, click here.

Below is a view of the current site showing the latest thinking about the location and configuration of the temporary school and parking lot (inside the red circle). Once the final contract has been awarded for the modular units, the construction schedule will be updated, and we will begin to share information about what we can all expect when we drive onto the campus after the 4th of July.


Upcoming meetings:

  • April 3rd, Power Purchase Agreement Subcommittee, 7:30am, Hartwell multipurpose room.
  • April 10th, School Building Committee, 7:00pm, Hartwell multipurpose room.
  • April 11th, Outreach Subcommittee, 11:00am, Hartwell multipurpose room.
  • April 22nd, Site Subcommittee, 9:00am, Hartwel multipurpose room.

Update from Town Meeting 2019

For the first time in…a long time…there was no school project presentation or vote at Town Meeting. However, there were two warrant articles with ties to the project:

  • Property Tax Study Committee: In February, the Selectmen (BOS) appointed the Study Committee, which is charged with examining existing tax abatement/deferral programs, determining unmet needs, investigating other possible programs, and making recommendations to the BOS. Click here to see the slides from Town Meeting.
  • Solar Bylaw: Lincoln first adopted a solar bylaw about a decade ago. Since then, both photovoltaic (PV) technology and the financial arrangements for installing PV panels have changed. Town Meeting voted to amend the current solar bylaw to allow residents, businesses, and the Town to enter into power purchase agreements (PPAs). This was a critical vote for the school project, and it was approved virtually unanimously. To learn more about how the bylaw was changed, visit the FAQ page on the Town website.

This Week’s SBC Meeting: The SBC will meet on Wednesday, March 27th @ 7:00pm, Hartwell multipurpose room. The agenda includes:

  • Review site and floor plans
  • Review exterior elevations
  • Review HVAC systems
  • Review monthly budget update
  • Review updated modulars plan (temporary classrooms)

If Sustainability is Important to You…

…or you just love learning about mechanical and building systems, this is the meeting for you!

SBC Meeting this Wednesday! (February 13th)

7:00pm, Hartwell Multipurpose Room

On the Agenda:

  • Introduce the Commissioning Agent (person who oversees the execution of all the detailed work that must be done to meet our sustainability goals)
  • Review the Owner’s Project Requirements (The “OPR” is the document that lays out general and specific sustainability goals for the project)
  • Review proposed MEP (mechanical, electrical & plumbing) systems
  • Review the progress of the Energy Model (are we meeting our energy use target?)
  • Review updated site plan

More about Sustainability…

On February 1st, representatives from the SBC, design team, Lincoln boards and committees, and Eversource, met to talk about all the aspects of the project that fall under the “sustainability” umbrella: the draft OPR, the negotiation of a Power Purchase Agreement, stormwater treatment, and mechanical systems.  Achieving net zero in a renovation project is a cutting edge concept for public schools in the state, and the message from Eversource was that they recognize our efforts, and are willing to partner with the Town and the design team to support the project in some unprecedented ways. Representatives from Eversource talked the group through the kinds of rebates that may be available to the Town (see the presentation from Eversource here).

Here is a summary of the technical assistance offered by Eversource:

HAPPY SUPER BOWL SUNDAY!

Due to February school vacation, the SBC meeting schedule is off of its every-other-week pattern.

The next SBC meeting is on Wednesday, February 13th at 7:00pm in the Hartwell multipurpose room. 

Plenty of work is still going on! This week:

Tuesday: SMMA & SBC present project plans to the Lincoln Historical Commission.

Wednesday: Site Plan working group.

Thursday: Outreach Sub Committee meeting.

Not Our First Rodeo…

Interior DesignAt the January 23rd SBC meeting, the SBC got a look at design concepts for the the interior of the school.  SMMA talked about choosing interior finishes that 1) create a calmer visual environment; 2) are durable; and 3) stay within our budget. This is made a bit more challenging by the fact that this is a renovation project, and that a number of colorful items will remain in place (i.e. teal countertops and cabinets in some rooms). As the interior is planned, it is important to think about future repairs and replacement when choosing the finishes, and later, the furniture. For example, we don’t want to specify 400 kiwi green chairs only to discover that a) the color will soon be discontinued, or b) that in a few years the “kiwi” of 2019 reminds us too much of the “avocado” of 1979. Fortunately, our administrative team has spent the last several years making these kinds of decisions for the Hanscom Primary and Middle Schools. We are able to draw on this depth of experience and the lessons learned.

Project ScheduleOur Construction Manager, Consigli, presented two important pieces of information at the meeting:

  1. Their cost estimate for the project (based on the Schematic Design phase) came in at essentially the same cost as the prior two estimates by SMMA and Daedalus. There will be another round of cost estimates in late March at the end of the Design Development phase.
  2. Consigli believes that the project can be completed by the start of the 2022/23 school year.  This is about six months earlier than previously planned (the image above shows a comparison of the old and new project schedules). This is one advantage of using a construction manager versus the “design, bid, build” construction method. Consigli is on board now, is part of the detailed investigation of existing conditions, and can help solve problems before difficult (or costly) issues arise.

Site Work: A Site Plan working group was brought together to think through refinements to the site plan. The initial meeting included representation from SMMA, Daedalus, the administrative team, the Conservation Commission, Parks & Recreation, the Roadway & Traffic Committee, the Cycling Safety Committee, and the SBC. The group will examine site related issues and bring ideas and recommendations to the SBC for its consideration.

Making Progress…

The Design Development phase is defined by a continuous series of design refinements, feedback, and decisions. At Wednesday’s SBC meeting, the committee reviewed a couple of different roofline options for the Learning Commons, and considered several possible design directions for the pathways and courtyards on both the east and west sides of the new main entrance.

Learning Commons: After reviewing both “gable” roof and “hipped” roof schemes, the SBC voted to direct the design team to continue to develop the gable roof option. The image above shows the latest iteration of the Learning Commons and main entrance – the design will continue to evolve.

Site PlanSMMA presented three variations of the pathways and courtyards adjacent to the main entrance/Learning Commons. The image above shows the general design direction chosen by the SBC. It features courtyards that flank the Learning Commons both to the east (front) and west (back) of the building. The courtyard in front is envisioned as a more public community space, while the courtyard in the back is seen as being more student-centered (or “business in the front, party in the back” as someone vividly described it!) This design, too, will continue to be developed and refined over time.

NOTE: The SBC learned that this was the last time we would be  joined by Samantha Farrell, Landscape Designer, SMMA, who will be moving out of Massachusetts. We want to express our gratitude to Ms. Farrell for her work on the project, and extend our best wishes to her as she embarks on her next adventure!

Exterior Building MaterialsSMMA and EwingCole presented a number of images and ideas for the exterior finishes of the building.  It is proposed that the school remain a primarily brick building with accent materials in selected areas of the building. Click here to see the complete slide deck from the meeting.

Working Group UpdatesThere are several working groups that are addressing specific aspects of the project. This work will then be reviewed and approved by the full SBC.

  • Education Working Group: This is comprised of members of the school’s administrative team and the design team. In December, SMMA met with teams of teachers to discuss specific and detailed needs. This information informs the development of the school’s interior spaces.
  • Power Purchase Agreement (PPA) Working Group: This group includes committee and community members who have an interest and/or experience in solar energy contracts. The group is working with a solar energy consultant to understand how best to structure an a PPA that meets our energy generation needs and is economically advantageous. The PPA Group is meeting weekly on Wednesday mornings at 8am in the Hartwell multipurpose room.
  • Sustainability Working Group: This group has multiple tasks: 1) Finalize the draft of the “Owners Project Requirements” (OPR) document that outlines the Town’s goals for the project – energy performance, indoor environment quality, water use and stormwater treatment, etc.; 2) Review and recommend to the SBC specific mechanical, electrical, and plumbing systems; 3) Interview and recommend to the SBC a “Commissioning Agent” who will be responsible for ensuring that the design and construction are meeting the goals of the OPR.

Upcoming Meetings:

  • PPA Meeting – Wednesday, January 16th, 8:00am, Hartwell multipurpose room.
  • SBC Meeting – Wednesday, January 23rd, 7:00pm, Hartwell multipurpose room.
  • Sustainability Meeting – Friday, February 1st, 8:00am, Hartwell multipurpose room. This meeting will bring together the design team, relevant town boards, and representatives from Eversource. The goal is to provide an overview of all the components that come under the “sustainability” umbrella, review who is responsible for each piece of the puzzle, and to identify any additional questions or tasks that may need to be addressed.
%d bloggers like this: