Skip to content Skip to left sidebar Skip to footer

Latest News

Exterior Update

Last Wednesday, while the sun was still up, the SBC spent part of its meeting outside looking at proposed exterior materials in natural light. As a result, the SBC approved 1) a red brick that mimics the brick on the current Smith School; 2) a dark, warm gray accent brick; and 3) a pallet of three cement board colors that will be used on the upper portions of the Auditorium and Reed Gym.

In addition, SMMA presented an updated HVAC plan.

Click here to see the entire slide deck from the meeting.

NEXT MEETING: Wednesday, August 14, 7pm, Hartwell.

We Choose…(the Sequel)

“We choose to go to the Moon! …We choose to go to the Moon in this decade and do the other things, not because they are easy, but because they are hard; because that goal will serve to organize and measure the best of our energies and skills, because that challenge is one that we are willing to accept, one we are unwilling to postpone, and one we intend to win …”

President John F. Kennedy, September 12, 1962

“As a Town, we always knew that developing a Lincoln School project would be complicated and require a careful cost/benefit analysis of criteria and options.“ — SBC blog post, December 2017

There’s no sugar-coating this: Last night’s School Building Committee (SBC) meeting was rough. Most of the construction bids are in and we had to vote to remove $3.5M from the project in order to keep us on time and on budget — REALLY?!?! So how did we get here, what did we have to cut, and what comes next?

Over two years ago, we got our first cost estimates for a set of project concepts based on our educational and sustainability ideals — they were much higher than we had hoped and the long, hard work of shaping and approving our school project began. Since June 2018, when we approved concept “L3” with a budget of $93.9M, we have had 4 sets of cost estimates and 3 rounds of value engineering. When making these painful decisions, we’ve relied on our community’s 5 core project values to guide our decisions about what we could cut. When we eliminated a final $1.1M at the end of November, we believed we had done everything we needed to do to get favorable bids from all the subcontractors involved in the project. The marketplace just told us otherwise.

Why are the bids high when we just did Value Engineering 2 months ago?

  • Our Construction Manager, Consigli, reminded us that this is a complicated renovation project which is harder to execute than new construction.
  • There are many new construction projects in the marketplace — other schools, housing, commercial, etc. — these projects are easier to estimate because there are fewer unknowns and there is less risk assumed by the contractors. As a result, in a white-hot construction market, contractors are more interested in these “clean” projects.
  • Annual escalation rates jumped from 5-6% in 2019 to 8% in the last two months.
  • There was a lower-than-expected response from our pre-qualified bidders. Only about half of the subcontractors ended up submitting a bid.
  • “Trade” contractors (e.g. roofing, plumbing, mechanical and electrical systems) had a hard bid deadline of January 29th. Trade bids are regulated by state laws that fix the scope of the work and preclude us from negotiating.
  • “Non-trade” contractors (e.g. steel, drywall, landscaping) are still able to submit bids for another couple of weeks. Consigli manages these bids.
  • We are committed to a project that is on time and on budget. The Committee made the hard decisions we needed to last night to cut what was necessary in order to close the gap, stay on budget, and keep us on schedule.

What did we have to cut? Unlike our other Value Engineering exercises, the size of the bid gap left the SBC with little discretion about what to remove. We had to make cuts in items that impact our project values such as: auditorium renovations/theatrical rigging; design features that admit and control natural light; a 3/4 reduction in the furniture, fixtures, equipment, technology budget; elimination of walkway and bike paths, courtyards; a 50% reduction of playground equipment, and; planting new trees.

The good news is that we protected key educational elements and the building remains net zero.

Next Steps:

  • Consigli will provide a breakdown of construction timing for each item that was value engineered/eliminated to help the SBC understand which decisions can/cannot be reconsidered if there are savings in other areas.
  • After school vacation week, the SBC will meet with the Finance Committee to see if there are any funding options, with minimal or no impact on the town budget, for funding core elements that affect long-term value and cannot be added after the project is complete. Any such funding decisions would require a Town Meeting vote.
  • Since the warrant for the Annual Town Meeting has closed, a Special Town Meeting (within the Annual Town Meeting) would need to be called for any project-related appropriations. The SBC voted to ask the School Committee to ask the Board of Selectmen to consider authorizing a STM if such a meeting is requested.
  • Upcoming meetings:
    • February 24th — School Committee Meeting, 8:00am; Board of Selectmen Meeting 6:30pm
    • February 25th — Finance Committee Meeting, 6:30pm
    • February 26th — School Building Committee Meeting, 7:00pm
    • February 27th — School Committee Meeting, 7:00pm

Meeting Postponed until February 12th

Tomorrow’s (Wednesday’s) SBC meeting has been postponed until next Wednesday, February 12th, 7:00pm, Hartwell multipurpose room.

The main purpose of tomorrow’s meeting was going to be to review the outcome of the Trade Bids process and the result of the Consigli non-trade bids. At this time, work is still being done to verify and qualify the bids in order to determine final costs versus estimates and total budget. The meeting is being moved to the 12th in order to give Consigli, SMMA, and Daedalus time to provide a more complete report on the process and outcomes of the bids.

Wednesday SBC Meeting – Construction Bids

SBC Meeting – Wednesday, February 5th, 7:00pm, Hartwell Multipurpose Room

Included on the Agenda:

  • Review Status of Trade/Non-Trade Construction Bids
  • Construction Update
  • Owner’s Project Manager Update

MEETING DATE CORRECTION: The next SBC meeting will be on February 26th (not the 19th). For a list of upcoming meetings, click here.

Circle the date…

…January 29th is a milestone day for the project! It is the day the trade bids will be opened, a key step in finalizing the “guaranteed maximum price” (GMP). Below is an overview of the project schedule.

At the February 5th SBC meeting, the project team will seek approval to award some or all of the trade contracts, which will allow the trade contractors to work on shop drawings, coordinate with Consigli, etc.


Project Progress

  • The temporary school now has electricity and safety testing has been completed.
  • The temporary school will be substantially complete by the end of January.
  • Paving of the temporary parking lot will be done in the spring.
  • The construction fencing around the temporary school will remain in place until the spring.

Next SBC Meetings

  • Wednesday, February 5th, 7:00pm, Hartwell Multipurpose Room
  • Wednesday, February 26th, 7:00pm, Hartwell Multipurpose Room
  • Note: The next SBC blog post will come out on February 2nd.

Reminder…the 4th of July fireworks display is cancelled for the next several years as the building project is completed and the playing fields restored. All the other fabulous July 4th activities will still take place!

Happy Holidays from the SBC!

Project Updates — from last week’s SBC meeting:

The piles of sub-trade submissions
  • The project has nearly completed the permitting process with both the Conservation Commission and the Planning Board.
  • The SBC voted to approve a list of over 100 companies to be in the pool of pre-qualified sub-trades. The construction bid documents will be released on December 18th and bids are due on January 29th.
  • Contract negotiations with SunPower for a Power Purchase Agreement (PPA) continue — many thanks to the PPA sub group that has been working hard on the details!
  • Due to the snow, the paving of the temporary parking lot is being postponed until the spring.
  • The link to Daedalus’ project update is here.

2020 SBC Meeting Dates: All meetings will be held in the Hartwell multipurpose room.

  • Wednesday, January 8th, 7:00pm
  • Wednesday, February 5th, 7:00pm
  • Wednesday, February 26th, 7:00pm

Until the New Year! The Outreach team is taking a break for the rest of the year and will start up again with a post on Sunday, January 5, 2020. We wish everyone a safe, healthy, relaxing, joyous holiday season and all the best in the New Year!

A year ago today…

…we gathered for the Special Town Meeting to approve the funding for the school project! A year later, the final bid documents are almost ready and the temporary home of our K-4 students is being completed. Our faculty is already preparing for the move which will take place when the school year is over in June. Here’s a glimpse inside the temporary school (photos courtesy of Principal Sarah Collmer):

The photos show a typical classroom, a connecting hallway, the view from what will become Principal Collmer’s office, and a view into her office.


Next SBC Meeting:

Wednesday, December 4th, 7:00pm, Hartwell multipurpose room. Click here for the agenda.

Budget Update

We are pleased to report that we’ve completed value engineering (VE) for the “90% Construction Document” phase. Our school building project remains on time and within budget. The next steps (proceeding through December) include finalizing plans and the 100% Construction Document drawings (Bid Documents) in preparation for soliciting sub-trade bids.  

Just as we did at the end of the “60% Construction Document” phase in September, the SBC made a number of difficult but necessary tradeoffs to keep the project on budget and to ensure we are getting the best value for our money. As they have been at each phase, decisions were guided by our project values: transform the educational environment, make the building net zero, recognize the school as a community asset, ensure that decisions are based on long-term value.

Our project is very complex and these cost deliberations are not always easy or straightforward.  For example, originally the project specified permeable pavement for the access road behind the school because the access road is in the wetland buffer zone and permeable pavement would allow water to percolate back into the soil.  However, after discussions with our Conservation Commission and the City of Cambridge (we are in the watershed for Cambridge’s supply, so it is within their purview to review site plans that impact the watershed), it was agreed that more conventional pavement is preferable in case of a spilled contaminant. Not only was this change better for protecting the wetlands and watershed, it, along with some other site work refinements, saved $167K in the construction budget.

Other VE decisions included:

  • Changing the size of ceiling panels in the Dining Commons from 2’ x 8’ to 2’ x 2’ ($41K)
  • Simplifying the roof blocking plan for all sloped roof eaves ($69K)
  • Changing the type of coat cubby that will be installed for grades K-2 (out of a total of $141K, took an $81K reduction from construction budget, kept $30K for installation, and put $30K into the furniture/fixtures budget)
  • Reducing the scope of kitchen equipment that needs to have an exhaust system ($8.5K)

In addition, several items were put on an “add-alternate” list. These are items that will be added back into the project if bids are favorable and/or there are contingency dollars left at the end of the project:

  • New divider for the Auditorium (separates the Lecture Hall from the rest of the Auditorium)
  • Roof screens to hide HVAC mechanical equipment.
  • 1/2 basketball court outside Reed Gym

From Superintendent Becky McFall

PROJECT UPDATE: Temporary Parking Lot Paving

Aggregate Industries was recently on site to review the porous paving operation for the temporary parking lot and sidewalks around the modular building. What to expect during the paving:

  • 2-3 trucks/per hour with an expected total of 15-20 trucks a day
    • Delivery of asphalt during the hours of school drop off and pick up is prohibited
    • Trucks will be timed so they are not staged on Ballfield Road.
  • Consigli Construction will be utilizing 4 parking spots in front of the Smith entrance alongside the field for the asphalt truck while they are paving the sidewalk along the West portion of the site. Barrels and signage will be installed for clear notification of which spots will be utilized. 
  • If you are travelling to or from the Ballfield Road campus while school is in session, you should expect the possibility of delays due to increased truck traffic.

Preschool Students At Work! (reprinted with permission from the October 23rd Superintendent’s Bulletin)

90%

We are now almost at the end of the 90% Construction Drawings phase. The SBC met on Thursday evening to review interior finishes for the Auditorium and Learning Commons, get a project update, and to review the latest set of cost estimates. Another round of Value Engineering is needed to ensure the project stays on budget, and the SBC will meet on Wednesday, November 20th to do that work. The meeting will be at 7:00pm in the Hartwell Multipurpose room.

 

 

%d bloggers like this: