Skip to content Skip to left sidebar Skip to footer

Latest News

Exterior Update

Last Wednesday, while the sun was still up, the SBC spent part of its meeting outside looking at proposed exterior materials in natural light. As a result, the SBC approved 1) a red brick that mimics the brick on the current Smith School; 2) a dark, warm gray accent brick; and 3) a pallet of three cement board colors that will be used on the upper portions of the Auditorium and Reed Gym.

In addition, SMMA presented an updated HVAC plan.

Click here to see the entire slide deck from the meeting.

NEXT MEETING: Wednesday, August 14, 7pm, Hartwell.

A year ago today…

…we gathered for the Special Town Meeting to approve the funding for the school project! A year later, the final bid documents are almost ready and the temporary home of our K-4 students is being completed. Our faculty is already preparing for the move which will take place when the school year is over in June. Here’s a glimpse inside the temporary school (photos courtesy of Principal Sarah Collmer):

The photos show a typical classroom, a connecting hallway, the view from what will become Principal Collmer’s office, and a view into her office.


Next SBC Meeting:

Wednesday, December 4th, 7:00pm, Hartwell multipurpose room. Click here for the agenda.

Budget Update

We are pleased to report that we’ve completed value engineering (VE) for the “90% Construction Document” phase. Our school building project remains on time and within budget. The next steps (proceeding through December) include finalizing plans and the 100% Construction Document drawings (Bid Documents) in preparation for soliciting sub-trade bids.  

Just as we did at the end of the “60% Construction Document” phase in September, the SBC made a number of difficult but necessary tradeoffs to keep the project on budget and to ensure we are getting the best value for our money. As they have been at each phase, decisions were guided by our project values: transform the educational environment, make the building net zero, recognize the school as a community asset, ensure that decisions are based on long-term value.

Our project is very complex and these cost deliberations are not always easy or straightforward.  For example, originally the project specified permeable pavement for the access road behind the school because the access road is in the wetland buffer zone and permeable pavement would allow water to percolate back into the soil.  However, after discussions with our Conservation Commission and the City of Cambridge (we are in the watershed for Cambridge’s supply, so it is within their purview to review site plans that impact the watershed), it was agreed that more conventional pavement is preferable in case of a spilled contaminant. Not only was this change better for protecting the wetlands and watershed, it, along with some other site work refinements, saved $167K in the construction budget.

Other VE decisions included:

  • Changing the size of ceiling panels in the Dining Commons from 2’ x 8’ to 2’ x 2’ ($41K)
  • Simplifying the roof blocking plan for all sloped roof eaves ($69K)
  • Changing the type of coat cubby that will be installed for grades K-2 (out of a total of $141K, took an $81K reduction from construction budget, kept $30K for installation, and put $30K into the furniture/fixtures budget)
  • Reducing the scope of kitchen equipment that needs to have an exhaust system ($8.5K)

In addition, several items were put on an “add-alternate” list. These are items that will be added back into the project if bids are favorable and/or there are contingency dollars left at the end of the project:

  • New divider for the Auditorium (separates the Lecture Hall from the rest of the Auditorium)
  • Roof screens to hide HVAC mechanical equipment.
  • 1/2 basketball court outside Reed Gym

From Superintendent Becky McFall

PROJECT UPDATE: Temporary Parking Lot Paving

Aggregate Industries was recently on site to review the porous paving operation for the temporary parking lot and sidewalks around the modular building. What to expect during the paving:

  • 2-3 trucks/per hour with an expected total of 15-20 trucks a day
    • Delivery of asphalt during the hours of school drop off and pick up is prohibited
    • Trucks will be timed so they are not staged on Ballfield Road.
  • Consigli Construction will be utilizing 4 parking spots in front of the Smith entrance alongside the field for the asphalt truck while they are paving the sidewalk along the West portion of the site. Barrels and signage will be installed for clear notification of which spots will be utilized. 
  • If you are travelling to or from the Ballfield Road campus while school is in session, you should expect the possibility of delays due to increased truck traffic.

Preschool Students At Work! (reprinted with permission from the October 23rd Superintendent’s Bulletin)

90%

We are now almost at the end of the 90% Construction Drawings phase. The SBC met on Thursday evening to review interior finishes for the Auditorium and Learning Commons, get a project update, and to review the latest set of cost estimates. Another round of Value Engineering is needed to ensure the project stays on budget, and the SBC will meet on Wednesday, November 20th to do that work. The meeting will be at 7:00pm in the Hartwell Multipurpose room.

 

 

Project Update

From the Superintendent — Construction activities on the Ballfield Road campus October 30 through November 15:

NEW – A Temporary Parking Lot is being developed

All of the modular trailers are now set in place and seaming the classrooms together is being completed.  A corridor connecting two sections of the building is being constructed and the roofs are being refurbished.  Each of the trailers will be anchored to the foundation.

Work has begun to create a temporary parking lot that will serve the temporary K-4 school for the 2021 and 2022 school years.  Once the project is complete and the modular trailers have been removed, the parking lot will also be removed and the center field will be restored.  Paving of the parking lot is scheduled to take place on November 12th.

Please be aware that there may be increases in truck traffic as construction debris related to the setting of the trailers is removed from the site along with actions being taken associated with creating the parking lot.

What you won’t see is all of the work that is taking place to prepare the interior of the modular classrooms for use.  Over the next couple of months, the interior of the temporary building will be renovated and refurbished creating a “new school” for our use in August 2020.

Next SBC Meeting: THURSDAY, November 14th, 7:00pm, Hartwell multipurpose room.

This Saturday, November 2nd!

  • 9:00am — Special Town Meeting (times after this are approximate)
  • 9:30 — Welcome
  • 9:35 — School Project Update
  • 9:45 — Setting the Context
  • 10:00 — South Lincoln Zoning Proposals
  • 11:15 — Community Electricity Aggregation
  • 11:30 — Property Tax Study Committee Update
  • 12:15 — Open Forum

For more information, visit http://www.lincolntown.org/1115/2019-Special-Town-MeetingState-of-the-To

Nearing the end of the 90% Construction Documents Phase

The 90% Construction Documents (90%CDs) were submitted for a final round of cost estimates on October 15th, and the estimates will be presented to the SBC at its November 14th meeting. This is the last round of estimates before the bid documents are finalized in December.

Below is an outline of the project schedule and milestones. The entire Daedalus presentation can be found here.

Saturday, November 2nd, 9:00am: Special Town Meeting & State of the Town Meeting, Lincoln School Auditorium. The SBC will present a project update.

Settling into place…

All the modular units are in place, and work in underway to connect them. Each unit contains the halves of two classrooms and half a hallway, so when two get attached, they create two classrooms and a part of a hallway. All the units will be connected so that it is a self-contained K-4 building.

Dates to Note…

Inside & Out

At last week’s meeting, the SBC got a look at the latest refinements to the interior design of the school. The design and color palette will knit together the renovated and new portions of the building. The image above shows the new entry lobby of the school. See how this kind of ceiling looks in real life here, and see other interior images here.


As reported in earlier posts, the SBC went through a Value Engineering (VE) exercise at the end of the 60% Construction Documents Phase to keep the project on budget. The single biggest savings ($500K+) was achieved by replacing the proposed concrete panel system on the upper levels of the Auditorium and Reed with brick. On Wednesday, the SBC reviewed several brick options, and chose a contrasting brick that will complement the accent brick being used on other parts of the building. The 3 photos below show: 1) the current building; 2) the previous concrete panel design; and 3) the new proposal. Click here for the entire slide deck, and here for the monthly project budget report.

Current Auditorium & Reed Gym
Concrete panel system
Current design proposal

The SBC will now meet once per month. The next meeting is on Wednesday, October 16th, 7pm, Hartwell multipurpose room.

%d bloggers like this: