Skip to content Skip to left sidebar Skip to footer

Tag: Phasing

Tree Fund Grows

This week, the SBC was very pleased to receive news of a substantial, anonymous donation to the Class of 2020 Tree Fund! The SBC voted unanimously to ask the School Committee to accept this very generous gift!

Another piece of good news is that there have been minimal COVID costs added to the project thus far. The full report from our construction team can be seen here.

New and improved (temporary) kitchen: A temporary kitchen that will serve all grades was installed in the Smith Gym. Here are photos of the old kitchen…

And here’s a photo of new…

Now we learn our ABCs: Finally, if you check out the slide decks from our meetings, you’ll see that Consigli, our construction manager, has divided the building into sections labeled with letters. Here’s a reminder of what the letters mean…

What’s Happening…With Construction?…At Town Meeting?

Construction Phase Begins!

Faculty and staff have been very busy packing up the school! Grades K-4 are getting ready to move into the temporary school and grades 5-8 will move into Smith. On June 8th Brooks will be turned over to Consigli and will officially become a construction site. Between now and then, there is a lot going on. For those who like the details, click here for the 4-week look-ahead schedule.


Town Meeting is Saturday, June 13th, 9:30am, Hartwell Parking Lot

In March, the SBC had planned to request up to ~$2M to restore items to the project that were eliminated when the construction bids came in $3.5M over the final estimates. Because Town Meeting was postponed due to COVID-19 and with the revised guidance of the Finance Committee, the SBC took another look at the proposed list of items and has reduced its request to $829K. Originally, there were 19 items on the list, one of which was restored to the project through negotiations with a subcontractor (yippee!) The SBC looked at the remaining 18 and asked the following questions: 1) What is the decision deadline for the item? 2) Can the item be added at a later date? 3) If it can be added, what is the potential cost impact? Below are two charts that summarize that analysis. 

SBC Virtual Community Forums: Thursday, June 4th @ 1:00pm & Monday, June 8th @ 8:00pm – details TBA. Much more information about Town Meeting can be found at http://www.lincolntown.org/1116/2020-Annual-Town-Meeting

Just for Fun…

Town Meeting will be held outdoors under a tent in the Hartwell parking lot. How big do you think the tent is? Click here for the answer. 

Building in the Time of COVID-19

Project Progress: Over the past couple of weeks the temporary faculty parking lot has been paved and striped and the construction fencing around the temporary school has been coming down!

Packing Up: This week the Lincoln School staff began the process of packing their classrooms and offices for the upcoming move! With the school closure extended through the end of the school year, the administration worked with our team of architects from SMMA and Consigli Construction to create a plan to begin the move process in order to create more time for construction.
The Lincoln School was originally scheduled to be packed and moved by late June. The revised timeline now brings the completion of the move to the end of the first week of June allowing Consigli access to the building the week of June 8th. This will not affect the already established overall timeline of the project but will provide some additional time to allow for unexpected delays due to unforeseen conditions or potential work delays due to COVID-19. Consigli may begin work that will not interfere with the packing and move prior to June 8th. In order to ensure the safety of all of our staff involved with the packing and move, a comprehensive protocol was developed to make certain there is minimal contact between persons and that all surfaces are cleaned before and after each space is occupied. Small numbers of staff are scheduled throughout the building on specific days and times over the course of three weeks. When teachers are packing, their team members are covering remote learning from home for their students. This is a huge endeavor under challenging conditions. We owe a tremendous debt of gratitude to our Lincoln School faculty, staff, and administrators, as well as, our facilities and technology staff who are all going above and beyond to make this happen! We will be prepared to start the next school year in the temporary modular building and the Smith portion of the Lincoln School. – from Superintendent Becky McFall

Town Meeting/Town Election Update: The Town Moderator and Board of Selectmen have rescheduled Town Meeting for Saturday, June 13th and the Town Election for Monday, June 15th. As of now, the State of Emergency extends through May 18th. Because Lincoln had already signed a Town Meeting warrant back in February, we are required to hold Town Meeting within 30 days of the lifting of the State of Emergency. This is why the date was set for mid June. To meet the deadlines for holding a Town Meeting/Elections, Town boards and committees need to move full steam ahead to plan for both events. If the state of emergency is extended? Well…at least we’ll be prepared!

Meeting This Week! The SBC is meeting via Zoom this Wednesday, 7:00pm (Details to join the meeting will be posted along with the agenda on Monday. Visit https://www.lincnet.org/Page/4876.) In addition to a construction update, the main purpose of the meeting will be to review the list of value engineered items that the SBC had planned to bring to a vote in March. These are the ~$2M worth of items that were eliminated from the project to keep it on budget, but that the SBC decided were important to the long-term value of the project. At Wednesday’s meeting, the SBC will get an update from the Finance Committee about the current state of Town’s financial picture and discuss how best to move forward with that list.

Recap from 3/25 Virtual SBC Meeting

On Wednesday the SBC met via Zoom. The meeting was broadcast live (as usual) on Comcast channel 8 and Verizon channel 33, and the video of the meeting can be seen here: https://lincolntv.viebit.com/?folder=ALL

The main purpose of the meeting was to review and approve the guaranteed maximum price (GMP) for the project. There are several components to the GMP, including (slide deck is available here):

  • Construction Cost: $78,324,908
  • List of Allowances: $1,489,700 (work that is anticipated but not yet fully designed or scope that is not yet defined until the project begins)
  • Assumptions and Qualification: Clarifications made by the Construction Manager to demonstrate understanding of the scope of work and to supplement the information contained in the design documents.
  • Project Schedule: Anticipated start and completion dates, including important milestones:
    • Modular classrooms: Complete
    • Phase 1: Start, June 22, 2020; Substantial Completion, June 22, 2021
    • Phase 2: Start, July 8, 2021; Substantial Completion, July 8, 2022

The SBC voted to approve the GMP subject to final review of the contract by Town Counsel.

Happy Holidays from the SBC!

Project Updates — from last week’s SBC meeting:

The piles of sub-trade submissions
  • The project has nearly completed the permitting process with both the Conservation Commission and the Planning Board.
  • The SBC voted to approve a list of over 100 companies to be in the pool of pre-qualified sub-trades. The construction bid documents will be released on December 18th and bids are due on January 29th.
  • Contract negotiations with SunPower for a Power Purchase Agreement (PPA) continue — many thanks to the PPA sub group that has been working hard on the details!
  • Due to the snow, the paving of the temporary parking lot is being postponed until the spring.
  • The link to Daedalus’ project update is here.

2020 SBC Meeting Dates: All meetings will be held in the Hartwell multipurpose room.

  • Wednesday, January 8th, 7:00pm
  • Wednesday, February 5th, 7:00pm
  • Wednesday, February 26th, 7:00pm

Until the New Year! The Outreach team is taking a break for the rest of the year and will start up again with a post on Sunday, January 5, 2020. We wish everyone a safe, healthy, relaxing, joyous holiday season and all the best in the New Year!

A year ago today…

…we gathered for the Special Town Meeting to approve the funding for the school project! A year later, the final bid documents are almost ready and the temporary home of our K-4 students is being completed. Our faculty is already preparing for the move which will take place when the school year is over in June. Here’s a glimpse inside the temporary school (photos courtesy of Principal Sarah Collmer):

The photos show a typical classroom, a connecting hallway, the view from what will become Principal Collmer’s office, and a view into her office.


Next SBC Meeting:

Wednesday, December 4th, 7:00pm, Hartwell multipurpose room. Click here for the agenda.

90%

We are now almost at the end of the 90% Construction Drawings phase. The SBC met on Thursday evening to review interior finishes for the Auditorium and Learning Commons, get a project update, and to review the latest set of cost estimates. Another round of Value Engineering is needed to ensure the project stays on budget, and the SBC will meet on Wednesday, November 20th to do that work. The meeting will be at 7:00pm in the Hartwell Multipurpose room.

 

 

Project Update

From the Superintendent — Construction activities on the Ballfield Road campus October 30 through November 15:

NEW – A Temporary Parking Lot is being developed

All of the modular trailers are now set in place and seaming the classrooms together is being completed.  A corridor connecting two sections of the building is being constructed and the roofs are being refurbished.  Each of the trailers will be anchored to the foundation.

Work has begun to create a temporary parking lot that will serve the temporary K-4 school for the 2021 and 2022 school years.  Once the project is complete and the modular trailers have been removed, the parking lot will also be removed and the center field will be restored.  Paving of the parking lot is scheduled to take place on November 12th.

Please be aware that there may be increases in truck traffic as construction debris related to the setting of the trailers is removed from the site along with actions being taken associated with creating the parking lot.

What you won’t see is all of the work that is taking place to prepare the interior of the modular classrooms for use.  Over the next couple of months, the interior of the temporary building will be renovated and refurbished creating a “new school” for our use in August 2020.

Next SBC Meeting: THURSDAY, November 14th, 7:00pm, Hartwell multipurpose room.

This Saturday, November 2nd!

  • 9:00am — Special Town Meeting (times after this are approximate)
  • 9:30 — Welcome
  • 9:35 — School Project Update
  • 9:45 — Setting the Context
  • 10:00 — South Lincoln Zoning Proposals
  • 11:15 — Community Electricity Aggregation
  • 11:30 — Property Tax Study Committee Update
  • 12:15 — Open Forum

For more information, visit http://www.lincolntown.org/1115/2019-Special-Town-MeetingState-of-the-To

Settling into place…

All the modular units are in place, and work in underway to connect them. Each unit contains the halves of two classrooms and half a hallway, so when two get attached, they create two classrooms and a part of a hallway. All the units will be connected so that it is a self-contained K-4 building.

Dates to Note…

%d bloggers like this: