Making Progress…

The Design Development phase is defined by a continuous series of design refinements, feedback, and decisions. At Wednesday’s SBC meeting, the committee reviewed a couple of different roofline options for the Learning Commons, and considered several possible design directions for the pathways and courtyards on both the east and west sides of the new main entrance.

Learning Commons: After reviewing both “gable” roof and “hipped” roof schemes, the SBC voted to direct the design team to continue to develop the gable roof option. The image above shows the latest iteration of the Learning Commons and main entrance – the design will continue to evolve.

Site PlanSMMA presented three variations of the pathways and courtyards adjacent to the main entrance/Learning Commons. The image above shows the general design direction chosen by the SBC. It features courtyards that flank the Learning Commons both to the east (front) and west (back) of the building. The courtyard in front is envisioned as a more public community space, while the courtyard in the back is seen as being more student-centered (or “business in the front, party in the back” as someone vividly described it!) This design, too, will continue to be developed and refined over time.

NOTE: The SBC learned that this was the last time we would be  joined by Samantha Farrell, Landscape Designer, SMMA, who will be moving out of Massachusetts. We want to express our gratitude to Ms. Farrell for her work on the project, and extend our best wishes to her as she embarks on her next adventure!

Exterior Building MaterialsSMMA and EwingCole presented a number of images and ideas for the exterior finishes of the building.  It is proposed that the school remain a primarily brick building with accent materials in selected areas of the building. Click here to see the complete slide deck from the meeting.

Working Group UpdatesThere are several working groups that are addressing specific aspects of the project. This work will then be reviewed and approved by the full SBC.

  • Education Working Group: This is comprised of members of the school’s administrative team and the design team. In December, SMMA met with teams of teachers to discuss specific and detailed needs. This information informs the development of the school’s interior spaces.
  • Power Purchase Agreement (PPA) Working Group: This group includes committee and community members who have an interest and/or experience in solar energy contracts. The group is working with a solar energy consultant to understand how best to structure an a PPA that meets our energy generation needs and is economically advantageous. The PPA Group is meeting weekly on Wednesday mornings at 8am in the Hartwell multipurpose room.
  • Sustainability Working Group: This group has multiple tasks: 1) Finalize the draft of the “Owners Project Requirements” (OPR) document that outlines the Town’s goals for the project – energy performance, indoor environment quality, water use and stormwater treatment, etc.; 2) Review and recommend to the SBC specific mechanical, electrical, and plumbing systems; 3) Interview and recommend to the SBC a “Commissioning Agent” who will be responsible for ensuring that the design and construction are meeting the goals of the OPR.

Upcoming Meetings:

  • PPA Meeting – Wednesday, January 16th, 8:00am, Hartwell multipurpose room.
  • SBC Meeting – Wednesday, January 23rd, 7:00pm, Hartwell multipurpose room.
  • Sustainability Meeting – Friday, February 1st, 8:00am, Hartwell multipurpose room. This meeting will bring together the design team, relevant town boards, and representatives from Eversource. The goal is to provide an overview of all the components that come under the “sustainability” umbrella, review who is responsible for each piece of the puzzle, and to identify any additional questions or tasks that may need to be addressed.

1 Comment

  • I have heard disturbing comments about the longevity of solar panels being 10 years. The challenge is how and where to dispose of them when they need replacing. Is there someting I can read which addresses these issues?